FIELD NOTESWhy this view exists / what to try / what I learned
WHY

When you scale from one site to a portfolio, the map stops scaling and the table starts. This is the multi-pane view a PM uses at 7am to triage the entire morning before the first machine starts.

WHAT TO TRY

Sort the fleet table by any column. Filter the event stream by ERROR / WARN / INFO. Pick a different site in the left rail to scope context. Click a row to populate the right-side context panel.

WHAT I LEARNED

Information density is correct for operator consoles, but every dense element needs a clear hierarchy of escalation. Color, status pill, sort cue, and filter pill all carry weight; getting them quiet enough to not compete with content took six passes.

Command/PORTFOLIO/EX-01
LIVEnow
Sites3
Fleet8 / 9
CY today4,840
Alarms1
Watches5
Open Subs/RFIs11 / 5
Burn44%
SHOW9/ 9
IDSiteModelStateOperatorFuelCYRTKTask
DZ-01ATX-SBX-001CAT D6IDLEAUTO71.9%4951.4Final pass, finish grade
DZ-02TAY-RTC-014CAT D8TACTIVEAUTO71.9%4952.1Stripping topsoil, north stockpile
DZ-03ATX-DEM-007CAT D5ACTIVEAUTO71.9%4951.8Pad shaping to subgrade
EX-01ATX-SBX-001CAT 320 GCACTIVEAUTO71.9%7701.7Footing dig, north pad
EX-02TAY-RTC-014CAT 336ACTIVEAUTO71.9%7702.1Slot trench for storm line
EX-03ATX-DEM-007CAT 349ACTIVEAUTO71.9%7702.3Loading haul truck, bench grade
GR-01TAY-RTC-014John Deere 850KACTIVEAUTO71.9%6051.9Pad finish, slope 551 percent
SK-01ATX-SBX-001Bobcat T76ACTIVEAUTO71.9%2201.9Site cleanup, perimeter sweep
SK-02ATX-DEM-007CASE TR340ACTIVEAUTO71.9%2201.9Curb form prep
Event Stream14
  • 04:16:45ERRORCompaction A ALARM at 91.4 % (target 95)
  • 04:16:45WARNDensity FB-1 WATCH at 128.19 lb/ft3 (target 132)
  • 04:16:45WARNMoisture FB WATCH at 13.63 % (target 12.5)
  • 04:16:45WARNSlope incl DET-S2 WATCH at -0.67 deg (target 0)
  • 04:16:45WARNPPV S building WATCH at 0.74 ips (target 0.5)
  • 04:16:45WARNCompaction subgrade WATCH at 92.32 % (target 95)
  • 04:16:45WARNMilestone "Access road subgrade" AT RISK due 2026-05-30
  • 04:16:45WARNSubmittal S-019 (31 25 00) returned for revision
  • 04:16:45WARNSubmittal T-033 (31 25 00) returned for revision
  • 04:16:45INFORFI-007 open: Conflict between storm tie in invert and sanitary lateral (to Civil EOR, due 2026-05-07)
  • 04:16:45INFORFI-014 open: Confirm cut slope ratio at access road station 4+10 (to Geotech, due 2026-05-09)
  • 04:16:45INFORFI-019 open: Detention pond bottom elevation discrepancy (to Civil EOR, due 2026-05-12)
  • 04:16:45INFORFI-021 open: Material reuse criteria for blackland clay (to Geotech, due 2026-05-15)
  • 04:16:45INFORFI-023 open: Fire lane subgrade compaction acceptance criteria (to AHJ Williamson Co, due 2026-05-18)